As part of a gas plant upgrade project in Norway, ALE was contractedto remove three existing MEG train modules from the process area to a barge at the quayside in preparation for their demolition.
The three 100te modules were raised using conventional and climbing jacks, then weighed and loaded onto 12 lines of SPMT for transportation through the live gas plant to a barge before being demolished.