[Skip to content]

Monday 21 May 2012
.

Mackenstreet Bridge, The Netherlands

ALE successfully completed the load-out of the Mackenstreet Bridge using two 28-axle line, two 18-axle line and two 10-axle line SPMTs as well as a hydraulic skid shoe system.

The 4,180te bridge required a specific load transfer sequence to the skid shoes and sea fastening supports that saw the barge turned 90 degrees and positioned along the quay side for sea fastening once the trailers had been removed.

[ Zoom ]
Mackenstreet Bridge
[ Zoom ]
Mackenstreet Bridge 2