ALE installed 6 modules, with a maximum weight of 35te to Platform L10A, in the North Sea, Netherlands. Onshore the modules were positioned onto specially designed lifting frames and transported by boat to platform L10A.
Offshore the modules, along with the lifting frame they were secured to, were lifted from the supply boat by two, project specific, 20te winches and skidded off transverse into position.
The project was especially challenging due to the small working area and the offshore weather conditions.