The piles and jacket were transported to the quay, in Lamprell, Jebel Ali, U.A.E, and loaded-out onto a class 300 barge as part of the ONGC North Tapti Gas Field Development.
The Piles were transported using 24 axle-lines of SPMT, the Jacket, using 48 axle- lines of SPMT.
Method statements and engineering calculations were prepared and submitted to meet both the client's and the independent Marine Warranty Surveyor’s requirements.
ALE was also responsible for the barge management operations during the load-out, which included the mooring and ballasting of the barge.